2025-2029 Capital Improvement Plan
Hamlet Park Playground Replacement/NewPark ID Sign 2025 thru 2029 Capital Improvement Plan Shakopee, MN Project # PA-27-01 Project Name
Hamlet Park Playground Replacement/NewPark ID Sign
Total Project Cost
$180,000
Contact
Public Works Director
Department
Park Asset Internal Serv. Fund
Type
Neighborhood Park
Category
Public Works
Priority
3 - Want to do
Status
Active
Useful Life
25 years
Fund
Park Asset IS Fund
Project Code
PA2704
Description Originally built in 2002, complete replacement of the playground equipment, meet ADA requirements, surface material, drain tile, garabge cans, benchs, table and border sections if needed. Plus we willl update the park ID Sign to the new design which was began in 2023
Justification 25 year replacement cycle evaluated for parts availability and safety guidelines.
Expenditures
2025
2026
2027
2028
2029
Total
168,500 11,500 180,000
Equip/Vehicles/Furnishings Engineering/Administration
0 0 0
0 0 0
168,500 11,500 180,000
0 0 0
0 0 0
Total
Funding Sources
2025
2026
2027
2028
2029
Total
180,000 180,000
Park Asset Internal Service Fund
0 0
0 0
180,000 180,000
0 0
0 0
Total