Capital Improvement Plan City of Shakopee, Minnesota

Department Storm Drainage Fund

Contact Public Works Director

Type Improvement

Project #

Storm-22-004

Useful Life

Project Name Boiling Springs Area Drainage Improvements

Category Storm Sewer/Drainage

Priority 2 Important-Provide Efficienci

Accounting Code

Status Active

Fund Surface Water Fund

Description This project includes drainage improvements to the boiling springs area located south and west of Boiling Springs Lane and east of Stagecoach Road. Justification This is a landlocked area where there are frequent drainage and flooding issues that impact property resulting in the need of city assistance to help protect and mitigate flooding issues. The project will implement solutions to reduce the need for frequent city assistance and improve drainage and flooding. Total Project Cost: $750,000

Expenditures

Total

2022

2023

2024

2025

2026

Construction/Maintenance

175,000

175,000

Engineering/Administration

25,000

25,000

25,000

175,000

200,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

Storm Drainage Fund

25,000

175,000

200,000

25,000

175,000

200,000

Total

Budget Impact/Other A feasibility study was completed by AE2S for this area.