2022-2026 Capital Improvement Plan (Final)
thru 2022 2026
Capital Improvement Plan City of Shakopee, Minnesota
Department Storm Drainage Fund
Contact Public Works Director
Type Improvement
Project #
Storm-20-002
Useful Life
Project Name Drainage and Flood Prevention Improvements
Category Storm Sewer/Drainage
Priority 2 Important-Provide Efficienci
Accounting Code
Status Active
Fund Surface Water Fund
Total Project Cost: $750,000
Description Drainage and flood prevention improvements.
This project includes improvements to drainage and flooding issues at the following locations: 1. Larkspur Court dry pond flooding. 2. The alley northeast of the intersection of 6th Avenue East and Spencer Street South. 3. The alley southeast of the intersection of 7th Avenue West and Apgar Street South. 4. Pinewood Estates near Pinewood Drive and Shenandoah Drive.
Justification There are frequent drainage and flooding issues at these locations that impact property and alley flooding, resulting in the need of city assistance to help protect and mitigate flooding issues. These projects will implement solutions to reduce the need for frequent city assistance and address the drainage, flooding and safety issues.
Prior
Expenditures
Total
2022
2023
2024
2025
2026
210,000
Construction/Maintenance
140,000
140,000
Engineering/Administration
25,000
25,000
Total
165,000
165,000
Total
Prior
Funding Sources
Total
2022
2023
2024
2025
2026
210,000
Storm Drainage Fund
165,000
165,000
165,000
165,000
Total
Total
Budget Impact/Other