2022-2026 Capital Improvement Plan (Final)

thru 2022 2026

Capital Improvement Plan City of Shakopee, Minnesota

Department Sanitary Sewer Fund

Contact Public Works Director

Type Maintenance

Project #

Sewer-22-002

Useful Life 20

Project Name Southbridge Lift Station Rehab

Category Sanitary Sewer

Priority 1 Critical for Safety/Preservati

Accounting Code

Status Active

Fund Sanitary Sewer Fund

Description Rehabilitate the lift station pumps and controls. Replace the telemetry system and incorporate into the new, citywide SCADA system. The lift station was originally constructed in 2002. A lift station evaluation and feasibility will be completed in 2022 to fully determine needed rehabilitation. Justification The lift station will be 20 years old in 2022. Routine rehabilitation is needed to ensure the dependability of the sewer system. The new SCADA system for this lift station will improve reliability, backup, response time, and data collection resulting in a more safeguarded sewer system to minimize and avoid backups caused by lift station failure. Total Project Cost: $190,000

Expenditures

Total

2022

2023

2024

2025

2026

Improvements

165,000

165,000

Engineering/Administration

25,000

25,000

190,000

190,000

Total

Funding Sources

Total

2022

2023

2024

2025

2026

Sanitary Sewer Fund

190,000

190,000

190,000

190,000

Total

Budget Impact/Other

208