2025-2029 Capital Improvement Plan
2029 Full Depth Pavement Reconstruction 2025 thru 2029 Capital Improvement Plan Shakopee, MN Project # CIF-29-001 Project Name
2029 Full-Depth Pavement Reconstruction
Total Project Cost
$4,750,000
Department
Capital Improvements Fund
Type
Improvement
Category
Street Reconstruction
Priority
1 - Have to do
Status
Active
Useful Life
30 years
Fund
Capital Improvement Fund
Project Code
CI2801
Description
This project is for the full depth reconstruction of the bituminous roadway for 10th Avenue from Apgar Street to Marschall Road (CR17). As part of this project, a reduction from a 4-lane section to a 3-lane section and pedestrian improvements will be considered. The City will be applying for Safe Routes to School and Regional Solicitation funds to include the multi-modal improvements with the project. Additional storm sewer improvements as well as utility and curb and gutter repairs and improvements will be evaluated and included with this project. Funding is programmed in 2026 to prepare funding applications and complete preliminary engineering to determine the appropriate multi-modal improvements (completed with CIF-28-001).
Justification This is a continuation of the City's Pavement Preservation Program to maintain existing infrastructure.
Expenditures
2025
2026
2027
2028
2029
Total
3,950,000
Construction/Maintenance Engineering/Administration
0 0 0
0 0 0
0 0 0
0
3,950,000
800,000
350,000 350,000
450,000
Total
4,400,000
4,750,000
Funding Sources
2025
2026
2027
2028
2029
Total
4,275,000
Capital Improvement Fund
0 0 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
350,000
3,925,000
325,000 100,000 25,000 25,000
Special Assessments Storm Drainage Fund Cost Sharing, SPUC Sanitary Sewer Fund
0 0 0 0
325,000 100,000 25,000 25,000
Total
350,000
4,400,000
4,750,000
Budget Impact Required ADA improvements are generally unfunded mandates to improve accessibility and minimize liability.