2025-2029 Capital Improvement Plan
West End Regional Pond and Trunk Oversizing 2025 thru 2029 Project Details Shakopee, MN Project # Project Name Total Project Cost Department
Storm-26-001
West End Regional Pond and Trunk Oversizing
$450,000
Contact
City Engineer Improvement 2 - Smart to do
Storm Drainage Fund Storm Sewer/Drainage
Type
Category
Priority
Status
Active
Fund
Surface Water Fund
Project Code
SD2501
Description Oversizing of ponds and storm sewer for managing offsite stormwater runoff that will be coordinated with development.
Justification It is important to control rates to manage the stormwater system and protect/reduce the potential for flooding in the downstream stormwater system.
Expenditures
2025
2026 2027 2028 2029
Total
Construction/Maintenance Engineering/Administration
0 0 0
400,000 50,000 450,000
0 0 0
0 0 0
0 0 0
400,000
50,000
Total
450,000
Funding Sources
2025
2026 2027 2028 2029
Total
Storm Drainage Fund
0 0
450,000 450,000
0 0
0 0
0 0
450,000 450,000
Total
Budget Impact The oversizing of ponds and pipes will be coordinated with development. A feasibility study by Stantec partially funded through Watershed Based Implementation Funding was completed to determine if there is a water quality benefit opportunity with oversizing. As a result of the study, it was identified that the existing water quality benefits need to be preserved with development and that the oversizing is primarily for rate control and flood control.
Produced Using Plan-It CIP Software
234