L16 Dual Forcemain Improvements 2025 thru 2029 Capital Improvement Plan Shakopee, MN Project # Sewer-29-001 Project Name
L16 Dual Forcemain Improvements
Total Project Cost
$2,547,000
Contact
City Engineer
Department
Sanitary Sewer Fund
Type
Improvement
Category
Sanitary Sewer
Priority
2 - Smart to do
Status
Active
Useful Life
50 years
Description
Project includes constructing a redundant (dual) forcemain that carry's sewage from the L16 Lift Station. The project will allow for redundancy in case pumps fail or need to be maintained.
Justification
L16 pumps sewage from the majority of downtown Shakopee. Its operations are critical to ensuring adequate sewer service for Shakopee.
Expenditures
2025
2026
2027
2028
2029
Total
2,060,000
Construction/Maintenance Engineering/Administration
0 0
0 0 0 0
0
0
2,060,000
412,000 75,000
150,000
150,000
112,000
Planning/Design
75,000 75,000
0
0
0
Total
150,000
150,000
2,172,000
2,547,000
Funding Sources
2025 75,000 75,000
2026
2027
2028
2029
Total
2,547,000 2,547,000
Sanitary Sewer Fund
0 0
150,000 150,000
150,000 150,000
2,172,000 2,172,000
Total