Community Center Pool Heat Exchangers 2025 thru 2029 Capital Improvement Plan Shakopee, MN

Project #

BA-28-009

Project Name

Community Center Pool Heat Exchangers

Total Project Cost

$200,000

Contact

Parks & Recreation Director

Department

Building Internal Service Fund

Type

Community Center

Category

Facilities

Priority

2 Important-Provide Efficiencies/Return on Invest

Status

Active

Useful Life

20 years BA2809

Fund

Building Asset IS Fund

Project Code

Description Replace Community Center pool water heaters with heat exchangers.

Justification The Community Center currently relies on water heaters to heat the pool. These units are aging and in need of replacement. Replacing these units with heat exchangers will utilize the building boilers to heat the water rather than natural gas. The exchangers will heat more effectively and reduce the need for natural gas, thus reducing long-term costs and increasing efficiency. If grant funding is available for efficiency upgrades, the grants will be applied for and used to offset direct costs.

Expenditures

2025 2026 2027

2028 2029

Total

Equip/Vehicles/Furnishings

0 0

0 0

0 0

200,000 200,000

0 0

200,000 200,000

Total

Funding Sources

2025 2026 2027

2028 2029

Total

Building Internal Service Fund

0 0

0 0

0 0

200,000 200,000

0 0

200,000 200,000

Total