2025-2029 Capital Improvement Plan

Community Center/Ice Arena Exterior Paint 2025 thru 2029 Capital Improvement Plan Shakopee, MN

Project #

BA-25-006

Project Name

Community Center/Ice Arena Exterior Paint

Total Project Cost

$13,000

Contact

Assistant City Administrator

Department

Building Internal Service Fund

Type

Community Center

Category

Recreation

Priority

2 Important-Provide Efficiencies/Return on Invest

Status

Active

Useful Life

5 years BA2508

Fund

Building Asset IS Fund

Project Code

Description Painting the exterior of the Community Center and Ice Arena

Justification As part of the 2020 capital improvement plan, the exterior of the Community Center and Ice Arena was sanded and repainted to replace the original stain which did not seal well. Going forward, touch up painting will be necessary every five years or so to ensure the long term integrity of the wood under the paint.

Expenditures

2025 2026 2027 2028 2029

Total 13,000 13,000 Total 13,000 13,000

Construction/Maintenance

13,000 13,000

0 0

0 0

0 0

0 0

Total

Funding Sources

2025 2026 2027 2028 2029

Building Internal Service Fund

13,000 13,000

0 0

0 0

0 0

0 0

Total