2024-28 Capital Improvement Plan
2024 2028 thru
Capital Improvement Plan City of Shakopee, Minnesota
Storm Drainage Fund
Department
Contact Public Works Director
Improvement
Type
Storm-25-001
Project #
Useful Life
Project Name West End Regional Pond and Trunk Oversizing
Storm Sewer/Drainage
Category
Project Code SD2501
2 Important-Provide Efficienci
Accounting Code
Priority
Fund Surface Water Fund
Status Active
Total Project Cost: $450,000
Description Oversizing of ponds and storm sewer for managing offsite stormwater runoff that will be coordinated with development.
Justification I t is important to control rates to manage the stormwater system and protect/reduce the potential for flooding in the downstream stormwater system.
Expenditures
Total
2024
2025
2026
2027
2028
Construction/Maintenance
400,000
400,000
Engineering/Administration
50,000
50,000
450,000
450,000
Total
Funding Sources
Total
2024
2025
2026
2027
2028
Storm Drainage Fund
450,000
450,000
450,000
450,000
Total
Budget Impact/Other The oversizing of ponds and pipes will be coordinated with development. A feasibility study by Stantec partially funded through Watershed Based Implementation Funding was completed to determine if there is a water quality benefit opportunity with oversizing. As a result of the study, it was identified that there is not a water quality benefit to consider with the oversizing.