2020-24 Capital Improvement Plan
Capital Improvement Plan City of Shakopee, Minnesota
thru 2020 2024
Contact Public Works Director Department Storm Drainage Fund
Type Improvement
Project # Storm-22-002 Project Name Blue Lake Channel (East) Regional Storm Pond
Useful Life
Category Storm Sewer/Drainage
Priority 2 Important-Provide Efficienci
Accounting Code
Status Active
Fund Surface Water Fund
Description To construct a joint regional pond with the SMSC on the Blue Lake Channel Prior to out letting to the Prior Lake Channel Regional best management practice to implement for rate control, flood protection, and water quality Justification It is important to control rates to manage the stormwater system and protect/reduce the potential for flooding in the downstream Prior Lake Outlet Channel. If there is infiltration, the project may reduce cost share outlined in the Prior Lake Outlet Channel Agreement. This project can provide water quality benefits by reducing sediment and phosphorus to help meet water quality goals and NPDES MS4 requirements. Total Project Cost: $750,000
Expenditures
2020
2021
2022
2023
2024
Total
675,000 75,000 750,000
675,000 75,000 750,000
Construction/Maintenance Engineering/Administration
Total
Funding Sources
Total
2020
2021
2022
2023
2024
375,000 375,000 750,000
375,000 375,000 750,000
Grants
Storm Drainage Fund
Total
Budget Impact/Other Joint Powers Agreement with the SMSC would be necessary on this joint venture. Feasibility project funded through WBF will identify water quality benefit and cost estimate to be completed 2018-2019.